Memphis district places new Frayser highschool on maintain


After years of advocating for the development of a state-of-the-art highschool in Memphis’ Frayser neighborhood, Regenia Dowell thought it was lastly going to occur this spring.

In tandem with its 2022-23 funds authorized in Could, Memphis-Shelby County Colleges officers proposed spending about $22 million to interrupt floor on a substitute for Trezevant Excessive College, which has one of many highest deferred upkeep payments of every other public college within the metropolis.

However that proposal hinged on the district’s request for $55 million in capital enchancment funds from Shelby County. When commissioners determined this month to grant MSCS lower than half that quantity, district officers have been compelled to place off the venture for at the very least one other 12 months. Dowell was heartbroken.

“It’s laborious while you’ve been working all these years and you may see it, however you may’t contact it,” stated Dowell, treasurer of the Frayser neighborhood’s parent-teacher-student affiliation. “Our youngsters want this; they should know they’re valued. They see different colleges and see that their college is just not practically as good as these colleges. Why can’t or not it’s like that right here?”

The brand new Frayser highschool is certainly one of a number of MSCS development tasks presently paused because the district dials again its capital spending plans in response to the funding setback. On Tuesday, throughout a specifically referred to as assembly, the MSCS board unanimously authorized a revised $2.1 billion funds that places these tasks in limbo and strips out greater than $10 million in different deliberate tasks.

Directors had hoped the $55 million fiscal 12 months 2023 allotment can be the primary installment of a 10-year, $550 million dedication from the county to deal with many years of deferred facility upkeep and replace growing older college buildings. Over 33 MSCS colleges have been constructed earlier than 1950, that means the buildings are 70 or extra years previous.

“We’ve got children which are going into bogs that haven’t been renovated since 1950. They’re studying in science labs that haven’t been renovated since 1950,” Patrice Thomas, the district’s chief of workers, informed the County Fee throughout its June 6 assembly.

However the fee authorized solely $21 million of the $55 million request, calling on the district to liquidate property or construct its case for elevating taxes countywide to generate funds.

It marks the second 12 months that MSCS has needed to delay a number of flagship tasks from its Reimagining 901 college enchancment and facility plan. Final summer season, the county equally balked on the district’s $55 million request, citing the federal COVID reduction help flowing into the varsity system. Some commissioners additionally voiced concern in regards to the impact that degree of spending might have on the county’s funds and taxpayers. 

Frayser neighborhood involved about development delay

The present Trezevant Excessive College in Frayser serves greater than 500 college students throughout grades 9-12 — most of whom are Black and are available from low-income households.

The brand new highschool was to be the primary of 5 new colleges within the Reimagining 901 plan unveiled final 12 months, and was focused for 2025 completion at a projected price of about $89 million. 

The district deliberate to construct the varsity on current college property — both on the Trezevant web site or at Martin Luther King Preparatory Excessive College, a part of the Frayser Neighborhood Colleges constitution community.

Within the spring, the MSCS board agreed to spend about $3 million drafting designs and plans for the brand new campus. The board additionally spent hundreds of thousands to do the identical for 2 different proposed colleges: A Treadwell Okay-8 that might mix Treadwell elementary and center colleges, and an Orange Mound Okay-8 that might mix Bethel Grove, Cherokee, and Dunbar elementary colleges. These colleges had focused completion dates of 2026 and 2027, respectively.

The district’s $55 million request to the county referred to as for practically $22 million simply to interrupt floor on the Frayser highschool. But the county’s whole allocation to the district amounted to about $1 million lower than that.

Now, it’s unclear when MSCS will be capable of full the brand new Frayser highschool, or the following two colleges in line for development. Through the Tuesday board assembly, Toni Williams, the district’s chief monetary officer, stated she hopes to start development on the highschool in 2024.

However Dowell stays uneasy. Though district officers have assured her that they continue to be dedicated to the venture, she worries it gained’t occur until the County Fee has an enormous change of coronary heart in future years. 

Dowell needs MSCS might discover the funds for the varsity in its personal funds. 

“I really feel like we’re being held hostage right here in Frayser by the funding scenario,” she stated.

For Bobby White, founder and CEO of Frayser Neighborhood Colleges, the brand new college represented new potentialities for the youngsters of Frayser.

Whereas the neighborhood already has three excessive colleges — Frayser Neighborhood Colleges’ M.L.Okay Faculty Prep, Trezevant, and Memphis Enterprise Academy — White envisioned a complete highschool offering households with one other instructional possibility and youngsters with extra alternatives. 

For instance, he hoped extra college students would be capable of take courses in languages moreover Spanish — like Latin or Mandarin, as supplied in MSCS excessive colleges like White Station or Central, and have extra entry to varsity, profession and technical schooling programs, as in different Memphis colleges.

Nonetheless, White says he’s optimistic for the neighborhood he grew up in.

“We’re not going to permit this to derail our give attention to making an attempt to supply a top quality schooling at Trezevant, MLK, and (Memphis Enterprise Academy),” he stated.

Different modifications in revised funds

In MSCS’ revised 2022-23 college 12 months funds adopted Tuesday, officers additionally slashed $5 million of gymnasium and security renovations at Richland Elementary, one other $5 million for a brand new stadium at Tobey Park, and minimize about $480,000 from a stadium enchancment venture at Raleigh Egypt Excessive College.

Upkeep and facility improve tasks that stay within the district’s new capital enchancment funds for 2023 embrace: 

  • $5.1 million for brand new intercom techniques at a number of colleges
  • $5.1 million for brand new heating and air techniques at Snowden Okay-8
  • $3.1 million to interchange the roof at Peabody Elementary
  • $3 million to extend outside lighting at varied colleges
  • $1 million for the Raleigh Egypt stadium venture

In an interview final week, college board Vice Chair Althea Greene stated that she’s disillusioned MSCS didn’t get the entire funding it requested for, however that she understands that county commissioners have “far more asks than they’ve funds to disburse.”

She cautioned district households that considerations about college upkeep, modernization, and beautification tasks is probably not addressed as rapidly because the district had hoped.

“We are able to solely spend what’s allotted to us,” Greene informed Chalkbeat. “On the subject of deferred upkeep, we are going to proceed to be behind, as a result of we proceed to not get sufficient funding to get forward.”

Samantha West is a reporter for Chalkbeat Tennessee, the place she covers Okay-12 schooling in Memphis. Join with Samantha at swest@chalkbeat.org.